In process safety and risk reviews, credible deviations are the practical backbone for deciding which hazards deserve analytical attention and which do not. The term sounds simple, yet the judgment behind it can make or break the quality of a HAZOP, What‑If review, LOPA, or Bowtie study. In high-hazard sectors across the UAE—oil and gas, petrochemical, power generation, large-scale construction, logistics of dangerous goods—teams constantly balance thoroughness with focus. Getting “credibility” right is how you stay rigorous without diluting scarce resources on far-fetched hypotheticals.
This article unpacks how practitioners determine what is reasonably foreseeable, how to use evidence and operating context to support decisions, and how to document rationale so that auditors, regulators, and internal stakeholders can trust the result. Along the way, we will connect the concept to recognized methods (HAZOP, LOPA, QRA, Bowtie), functional safety expectations (IEC 61511), and regulatory frameworks that matter in the UAE. The aim is to help HSE managers, operations leaders, process engineers, and compliance officers make better calls—consistently—when deciding which scenarios are in and out of scope.
Who Does This Affect?

While the phrase is common in process safety circles, the judgment about “credibility” is shared across multiple functions. In practice, the people who wrestle with these calls include:
- HSE and process safety teams leading or facilitating HAZOP, HAZID, What‑If, LOPA, Bowtie, QRA, and ALARP demonstrations
- Operations and maintenance leaders who know how equipment behaves during start‑ups, shutdowns, trips, and abnormal conditions
- Process, instrumentation, and controls engineers responsible for BPCS logic, alarms, interlocks, and safety instrumented functions (SIF) under IEC 61511
- Asset integrity, reliability, and inspection teams (e.g., RBI, thickness monitoring, vibration analysis) who provide failure data and condition insights
- Turnaround and project engineers who must screen project hazards, hot work interfaces, and tie‑ins during brownfield modifications
- Logistics and warehousing supervisors handling dangerous goods, bulk transfers, and temporary operations
Beyond internal teams, credibility decisions are scrutinized by external stakeholders such as insurers and third-party verifiers, and they are of clear interest to UAE authorities and duty holders—ADNOC group companies and their contractors, OSHAD under Abu Dhabi Public Health Center for safety frameworks, Dubai Municipality for EHS oversight in industrial zones, and Civil Defence authorities for fire and life safety approvals. Each of these parties expects a defensible, documented rationale showing that major accident hazards have been fairly considered—neither ignored nor trivialized.
Why This Matters

After years of process safety practice, most facilities have learned that the biggest risk is not that a study misses an exotic, one‑in‑a‑billion scenario; it’s that teams get overwhelmed by noise and lose clarity on what truly threatens people, assets, and the environment. A disciplined stance on credibility serves several important objectives:
- Focus: Keeps workshops from ballooning into theoretical debates and forces attention to the failure modes that can realistically occur on this equipment, in this climate, with this operating culture.
- Compliance: Aligns with process safety regimes (e.g., OSHA PSM 1910.119’s hazard analysis thinking, COMAH‑style concepts in other jurisdictions) and helps make UAE regulatory interactions more productive.
- Functional Safety Integrity: Supports IEC 61511‑aligned justifications for SIF design by ensuring initiating event frequencies and scenarios are neither overstated nor understated.
- ALARP and Decision Quality: Builds a credible basis for “reasonably practicable” risk reduction and for prioritizing capital and maintenance resources.
- Auditability and Learning: Creates a record of why a scenario was included or excluded, enabling traceability, peer challenge, and continuous improvement after incidents or near misses.
Ultimately, deciding what is “credible” shapes the hazard inventory that feeds your safeguards, alarm strategies, maintenance intervals, emergency planning assumptions, and performance standards for barriers. It is not an academic exercise; it is a foundation for safe, reliable, and compliant operations.
Key Points to Understand

Building a defensible approach to credibility starts with consistent definitions, an agreed set of screening criteria, and a common understanding of how different analyses use the output (HAZOP nodes, LOPA initiating events, Bowtie top events, QRA release cases). Consider the following pillars:
1) What counts as a deviation vs. a scenario
A deviation is a departure from intended design or operation—no flow, more pressure, reverse flow, etc. A scenario pairs that deviation with initiating causes and the potential consequence path. For example, “more pressure” becomes a scenario when tied to a cause (blocked outlet), followed by a path (overpressure → relief to flare → potential PSV lifting failure → vessel rupture).
2) Reasonably foreseeable, not theoretically possible
Credibility is not about eliminating rare events. It is about eliminating events that have no plausible cause chain under realistic conditions. A meteor strike is not credible; a simultaneous utility failure during a sandstorm might be, depending on grid reliability and site experience.
3) Evidence-informed screening
Teams should draw on multiple sources: incident and near‑miss history (local and industry), CMMS and RBI data, OEM and generic reliability data, operating envelopes and procedures, environmental loads (heat, humidity, dust), human factors (shift work, simultaneous operations), and interdependency with adjacent systems. The aim is a reasoned narrative, not a guess.
4) Frequency bands and thresholds
Whether your organization uses qualitative categories (“Unlikely,” “Possible,” “Likely”) or quantitative estimates (per‑year initiating event frequencies), credibility screening benefits from benchmarks. Some companies adopt lower‑bound thresholds to filter astronomical combinations, while still capturing low‑frequency/high‑consequence cases if reasonably foreseeable. The point is consistency, not a specific number.
5) Safeguard independence and common cause
Deciding credibility involves the post‑cause world too. If two barriers share a common power source or human action, their combined failure may be more plausible than assumed. Treat safeguards per IEC 61511 expectations for independence and avoid granting credit to layers that can fail together under the same conditions.
6) Transitional states matter
Start‑ups, shutdowns, maintenance overrides, bypasses, and abnormal operations often produce a different risk picture than steady state. A deviation that seems far‑fetched during stable operation may be quite plausible during a compressor restart or a pigging campaign.
Practitioners can find methodological depth in resources like the Center for Chemical Process Safety (CCPS), which has long guided industry on hazard identification quality, scenario selection, and safeguard performance. While every site is unique, these principles help anchor credibility judgments in shared good practice.
| Element | What it means | Typical evidence sources | UAE‑specific considerations |
|---|---|---|---|
| Deviation statement | A concise departure from intended operation (e.g., “No flow,” “More temperature”). | P&IDs, procedures, operating envelopes, previous HAZOPs | Ambient heat effects on pumps/compressors; dust ingress impacting moving parts |
| Initiating causes | Specific triggers leading to the deviation. | OEM manuals, failure histories, CMMS work orders | Grid reliability and brownouts; saline corrosion in coastal sites |
| Screening criteria | Rules used to judge if the scenario is reasonably foreseeable. | Corporate risk policy, facilitator guide, CCPS guidance | Local regulatory expectations and ADNOC operator requirements |
| Frequency bands | Qualitative or quantitative likelihood ranges for initiating events. | Generic databases, site data, expert elicitation | Environmental loads (sandstorms), seasonal demand swings |
| Safeguard independence | Whether layers of protection can fail together (common cause). | Cause & effect, SRS, alarm rationalization | Shared utilities (instrument air, cooling water) in multi‑unit plants |
| Regulatory triggers | Obligations or thresholds activated by the scenario. | Company standards, authority approvals | Fire/egress per Civil Defence code; hazardous area compliance |
How This Works in Practice

Translating principles into clear decisions requires structure and discipline in workshops and in follow-up analysis. A workable rhythm looks like this:
- Start with the equipment and boundary. In HAZOP, that means a well-defined node with a known process intent and design limits.
- State the deviation simply. For example, “Reverse flow in reflux line.” Avoid embedding cause or judgment in the initial phrase.
- Generate plausible causes. Consider hardware failures, control logic states, human actions or omissions, and external stresses (utility upsets, weather, neighboring unit interfaces).
- Check against evidence. What has failed before? What maintenance findings hint at emerging failure modes? Are there vendor bulletins? How does this system behave during start‑up trips or after alarms?
- Challenge safeguards and independence. If two barriers share a PLC or a power supply, challenge their assumed independence. If an operator action is credited, ask whether alarm rationalization and staffing support it.
- Decide credibility and record rationale. If excluded, document the grounds (e.g., “requires three independent failures across separate layers with no credible common cause; no site or industry precedent”). If included, trace the potential consequence path and assess severity and risk reduction needs.
Real‑world examples bring the judgment to life:
- Refinery hydrotreater: “More pressure” due to blocked outlet is credible during fouling and turnaround close‑outs; the same deviation from a hypothetical, simultaneous PSV jam and relief flare total failure might not be—unless common cause (e.g., contamination, maintenance error) is shown plausible.
- Petrochemical cracked gas compressor: Surge during hot restart can credibly cause “No flow to downstream cooler,” but only under certain interlock bypasses and ambient conditions; that nuance matters for safeguards.
- Power and desalination: “No cooling water flow” during peak summer heat carries higher plausibility due to shared utilities and fouling—this elevates the weight given to related initiating events.
- Bulk chemicals logistics: “Release during road tanker offloading” may be credible due to hose failure or human error; a catastrophic release caused by a meteorological anomaly with no site precedent is not a good use of attention.
- Construction high‑rise: “Crane overload during gusting winds” is credible if weather patterns routinely exceed planning assumptions; a main boom collapse from a rare, out‑of-season cyclone might fall outside reasonable foreseeability—but should be revisited if regional patterns change.
The key in all cases is the traceable line from cause plausibility to decision, with local operating reality front and center. That same record supports later LOPA calculations (initiating event frequency and enabling conditions) and informs Bowtie barrier thinking—especially where human and organizational factors are at play.
Benefits and Practical Use Cases

Teams that treat credibility decisions as an evidence-informed discipline see tangible gains across the lifecycle of assets and operations:
- Sharper studies: HAZOP and What‑If sessions stay focused, making space to examine real safeguards (basic controls, trips, alarms, PSV sizing, procedures) in depth.
- Better interlock and SIF design: LOPA inputs grounded in realistic initiating events yield SIL targets that are fit‑for‑purpose and defendable at IEC 61511 audits.
- Prioritized maintenance and inspection: Credible failure paths drive RBI and CMMS attention to the right assets (e.g., check valves in critical reverse‑flow paths, instrument air dryers during humid months).
- Actionable emergency preparedness: Emergency drills, firewater flows, and mustering plans align to plausible release sizes and escalation patterns—not theoretical extremes.
- Smoother regulatory dialogue: When the inclusion/exclusion rationale is documented, interactions with ADNOC requirements, OSHAD frameworks, Dubai Municipality, and Civil Defence become more straightforward.
- Resilience to abnormal operation: Special attention to start‑ups, shutdowns, and simultaneous operations (SIMOPS) makes the overall risk profile more robust.
These benefits accrue when credibility filtering is consistent across projects and operations. EPC designs hand off to operations with a shared hazard picture; brownfield modifications reuse the same screening logic; audits find the same pattern of reasoning in different parts of the facility.
Best Practices and Points of Caution

Experienced teams institutionalize a few habits that keep credibility discipline strong and auditable:
- Anchor to a written screening policy: Define what “reasonably foreseeable” means in your company, with examples and thresholds (qualitative and/or quantitative).
- Triangulate evidence: Blend site history, industry data, OEM guidance, and expert judgment; avoid single‑source justifications.
- Respect independence: Apply IEC 61511 thinking to safeguard layers; do not double‑count barriers that share power, logic, or human intervention under the same stressors.
- Don’t neglect low‑frequency, high‑consequence events: If there is a plausible chain without multiple unlikely coincidences, include it—particularly where escalation can reach occupied buildings or offsite receptors.
- Elevate transitional states: Systematically consider start‑ups, shutdowns, maintenance overrides, and SIMOPS; log which scenarios are conditional on these states.
- Document exclusions with care: Record the reason, the data considered, and who concurred; this is invaluable when questions surface later.
- Revisit after change: Trigger a credibility recheck after MOC, incident learning, or environmental shifts (e.g., hotter summers, more frequent dust storms).
- Mind local context: In the UAE, heat, salt-laden air, and dust can shift failure probabilities; do not import overseas assumptions without adapting them.
For overarching context on how hazard analysis underpins regulated process safety management systems, see OSHA’s Process Safety Management standard. While frameworks differ across jurisdictions, the core discipline—identify hazards credibly, evaluate risks proportionately, manage change—remains consistent and recognized by global operators and regulators.
Frequently Asked Questions About Credible Deviations
What does “credible” actually mean in hazard studies?
Credible means reasonably foreseeable for your specific equipment, process, and context—based on evidence and sound engineering judgment. It excludes scenarios that require an implausible chain of independent failures or fantastical external events, but it includes rare events if there is a realistic cause path and potential for serious harm.
How do teams gather evidence to support credibility decisions?
Evidence comes from incident and near‑miss records, CMMS and inspection data, OEM documentation, reliability databases, operator interviews, alarm and trip histories, and environmental/load assessments. Cross-functional input—from operations, maintenance, process control, and safety—is essential to avoid blind spots.
Can a scenario involving multiple failures still be credible?
Yes, if the failures are not independent (e.g., a common power loss or maintenance error disabling redundant devices), or if each step is individually plausible and known to occur in combination under certain conditions (like start‑ups). The independence and common‑cause analysis often makes the difference.
How does this tie into LOPA and SIL determination?
LOPA uses initiating event frequencies and independent protection layers to estimate residual risk. If your initiating events aren’t credible—or if you misjudge barrier independence—your SIL targets can be mis-specified. Credibility screening ensures LOPA inputs reflect the real operating world and meet IEC 61511 expectations for evidence and independence.
How should exclusions be documented?
Each exclusion should include the scenario statement, the reason it was deemed not credible, the evidence considered, and the names/roles of those who agreed. Good practice is to capture this within the HAZOP or What‑If log (or a linked register) so it is auditable and easy to review during MOC or external assessments.
Do UAE authorities prescribe a definition of credibility?
Authorities emphasize robust hazard identification and risk management rather than prescribing one definition. However, ADNOC requirements, OSHAD frameworks, Dubai Municipality EHS expectations, and Civil Defence fire and life safety reviews all assume that major hazards have been credibly identified and addressed with appropriate safeguards and emergency measures.
Should environmental extremes be part of credibility assessments?
Absolutely. Heat, humidity, dust storms, and saline atmospheres can affect failure likelihoods (e.g., fouling, corrosion, motor derating). These conditions should be included explicitly in scenario screening and in assumptions about barrier performance, inspection, and maintenance.
How often should the credibility basis be revisited?
At a minimum, during periodic hazard study revalidations and after material changes through MOC. It should also be revisited following significant incidents, near misses, or new information (e.g., OEM bulletins, reliability alerts) that might shift initiating event likelihoods or barrier performance.
Conclusion
Determining what is credible is a practical art grounded in evidence, method, and local operating reality. When teams consistently apply clear screening rules, check independence of safeguards, account for transitional states, and document their reasoning, the result is a hazard inventory that truly guides design, operations, maintenance, and emergency planning. That discipline strengthens IEC 61511 alignment, supports ALARP demonstration, and makes regulatory conversations more straightforward—because the logic behind inclusions and exclusions is transparent and traceable. Whether you are running a refinery unit, a petrochemical compressor train, a power-and-water complex, or a hazardous goods terminal, credible deviations are the fulcrum that turns hazard identification into meaningful, risk-reducing action.
To go further on this topic, NPM’s broader What If Analysis Services UAE page covers this in more depth.
Our References
NPM’s experience with hazard identification and the disciplined screening of scenarios is reflected across a broad portfolio of projects worldwide, spanning upstream platforms, onshore terminals, refineries, petrochemical complexes, power generation and desalination assets, major construction undertakings, and high‑hazard logistics hubs. In our references, you will find examples of how a rigorous approach to “what is reasonably foreseeable” sharpened the scope of HAZOPs and What‑If reviews, made LOPA initiating event frequencies more defensible, and brought clarity to Bowtie analyses where organizational, procedural, and technical barriers intersect. These case insights show how cross‑functional teams aligned on a shared definition of credibility, used site evidence to support inclusion or exclusion, and documented rationale in a way that stood up to internal audits and external regulatory review. They also illustrate how credible scenario lists evolve through revalidation cycles, management of change, and incident learning—ensuring studies remain living, decision‑making tools rather than one‑time checklists. Whether the need was to resolve disagreements about low‑probability combinations, to adapt overseas assumptions to hotter, dustier climates, or to reconcile design intent with operator experience, NPM focused on traceable reasoning and measurable risk reduction. We invite you to explore these examples to see how disciplined credibility filtering translates into safer operations, smarter barrier design, and more focused investment in safeguards across industries and regions.
For more information about our references, visit Our References.
Speak with NPM
If you are refining your hazard identification approach or preparing for a study revalidation, our team is happy to discuss how credibility screening can be tailored to your facility and operating context. We welcome technical questions from HSE leaders, engineers, and operations teams who want to compare notes, pressure‑test assumptions, or align internal guidance. For any further questions or to speak with our team, Contact Us.